all articles

Project Management 101: What is PERT?

date icon

PERT stands for the Project Evaluation and Review Technique and is a graphical tool used to schedule, organize, and coordinate tasks. Its often used in conjunction with the critical path project management method.

Task Sequencing and Durations

One of PERTs key components is its use of nodes and arrows to represent task dependencies and sequences. Sequential tasks are indicated by connecting arrows, whose lengths also correspond to the task’s projected duration. Using these task sequences, project managers can identify and prioritize the critical path and plan the fastest possible route to project completion.

But where other planning diagrams use best-case scenarios in the planning phase, PERT takes a more skeptical and realistic approach. Each task in PERT has three time estimates: Optimal, Normal, and Pessimistic. These are used to compute for Expected Time, with the formula (O + 4M + P) 6. The result is then plugged into a visual chart such as the PERT diagram or even a Gantt chart. This way, the project manager has a more accurate overview of the project life cycle.

Pros and Cons

As already mentioned, PERT makes it easy to identify the critical path and the relationship between each task’s start and end dates, as well as the available slack for each path. And because you have a better understanding of each path’s dependencies, you can more easily shuffle tasks around to facilitate better resource management.

One of PERTs biggest drawbacks, however, is its tendency to grow unwieldy the more complex a project is. Some larger projects can have literally hundreds of tasks and dozens of paths, each with its own intersecting dependencies. When these complex diagrams become tangled and inconvenient, people stop using them making them moot. Also, it’s hard to track elapsed time or project progress with PERT diagrams.

Some project managers use a combination of Gantt charts and PERT diagrams. The Gantt charts track and manage project progress and scheduling, while the PERT diagram tracks task dependencies and the critical path.

As with every other project management tool, what to use depends on your organization’s unique situation and workflow. If no single project management method works for you, mix and match them. The only truly correct project management method is the one that helps you get your work done the fastest.

 

Follow us

Find Out How Easy Resource and Project Management Can Be!

Related Posts

Project Management Basics

Project management communication: Importance, Benefits, Steps and Best Practices

Best PracticesProject Management Basics

On-Premise Project Management Software in 2024: Must-Know Insights

Project Management Basics

Project Portfolio Management (PPM): The Ultimate Guide

Nice! You just took the first step to achieving game-changing results.

To ensure your demo is tailored to your team’s specific needs, we're connecting you with a product specialist to better understand your requirements.

support illustration

Schedule a 30-minute meeting to start your trial

The calendar is loading... Please wait

It’ll take you 8-minutes to see
Birdview features in action:

  • Project Management
  • Financial Management
  • Resource Management
  • Custom Reporting
  • Artificial Intelligence
happy illustration

Nice! You just took the first step
to achieving game-changing results!

Create your account right now. Have a great start with your 14-day trial!

For the best experience please access Birdview PSA from a desktop PC or tablet or download Birdview PSA app at