Project Finances Guide

Appendix: Project Finances Formulas

Sometimes project finances can get confusing, so feel free to use this guide as a reference for various financial metrics commonly used in project management.

Planned Labor Cost – a prediction of how much labor cost the project might need.

Planned Labor Cost = Estimated Hours x Internal Hourly Rate

 

Planned Expenses – a prediction of non-labor related costs the project might need.

 

Planned Project Cost – the expected total cost of the project at the very beginning of the project.

Planned Project Cost = Planned Labor Cost + Planned Expenses

 

Actual Labor Cost – the total cost of labor spent on the project to date.

Actual Labor Cost = Actual Number of Hours x Internal Hourly Rate

 

Actual Expenses – how much has been spent on project expenses to date.

 

Actual Project Cost – the real-time summary of the project’s actual labor costs and expenses once the project has started.

Actual Project Cost = Actual Labor Cost + Actual Expenses

 

Estimate at Completion (EAC) Labor Cost – the estimated total labor cost at the end of the project.

EAC Labor Cost = Actual Labor Cost + ETC Labor Cost

 

ETC Expenses – remaining expenses needed to complete the project.

 

ETC Project Cost – the real-time summary of the remaining estimated labor cost and planned expenses – what is left to complete the project.

ETC Project Cost = ETC Labor Cost + ETC Expenses

 

Estimate to Complete (ETC) Labor Cost – remaining labor cost needed to complete the project.

ETC Labor Cost = Hours Left x Internal Hourly Rate

 

EAC Expenses – estimated total expenses at the end of the project.

EAC Expenses = Actual Expenses + ETC Expenses

 

EAC Project Cost – estimated total cost at the end of the project.

EAC Project Cost = EAC Labor Cost + EAC Expenses

 

Remaining Budget – the amount left to complete the project.

Remaining Budget = Total Budgeted Cost – Actual Cost

 

Total Project Budgeted Cost – a set amount allocated to a project as a cost threshold that the Project Manager needs to remain under.

Total Project Budgeted Cost = Planned Project Cost + Contingency Padding

 

 

Actual Flat Fee Activities – the sum of all flat fees associated with billable activities that have been completed.

 

Actual Labor Billing – the amount of money matching the performed billable labor.

Actual Labor Billing = Actual Billable Hours x Billing Rate + Actual Flat Fee Activities

 

Actual Billable Expenses – the sum of all actual expenses that are billable to a customer.

 

EAC Billable Expenses – the sum of all billable expenses at the end of the project.

EAC Billable Expenses = Actual Billable Expenses + ETC Billable Expenses

 

Actual Profit Margin – real-time profitability of the project represented as a percentage.

Project Margin = Actual Project Profit / Actual Project Revenue * 100%

 

EAC Profit Margin – estimated profitability at the end of the project represented as a percentage.

EAC Project Margin = EAC Project Profit / EAC Project Revenue * 100%

Billed – total amount already billed to a customer.

 

Work in Progress (WIP) – shows how much work has been completed that has not been billed to the customer yet.

Work In Progress = (1 – (Total Billed / Total Project Billing)) * 100%

 

Cost Performance Index (CPI) – shows how well the project is performing relative to the project budget.

CPI = (Progress * Estimated Hours * 100) / Actual Hours

 

Schedule Performance Index (SPI) – shows how well the project is performing relative to the project schedule.

SPI = (Progress / 100) / (Current Date – Start Date) / (End Date – Start Date)

 

Utilization Rate – a ratio between the total billable hours spent by each resource to their available hours and is calculated as a percentage.

Utilization Rate = Billable Hours / Total Available Hours * 100%

 

Realization Rate – a ratio between total billed hours compared to the total available billable hours.

Realization Rate = Total Billed Hours / Total Billable Hours * 100%

 

Realized Rate – an effective billing rate based on the Realization Rate and your resources’ billing rate.

Realized Rate = Realization Rate * Billing Rate
Birdview logo
Nice! You’re almost there...

Start your 14-day trial and unlock its full potential by scheduling a 15-minute call with our Product Manager.

The calendar is loading... Please wait
Birdview logo
Great! You've just taken your first step towards game-changing results!
Start your Birdview journey with a short 9-min demo
Watch demo video