How to handle resource shortages in critical phases

Resource gaps often show up at the worst time: right before cutover, during testing, or at a milestone review. The goal is simple: keep delivery on track without burning the team or the budget. The steps below help you decide fast, keep changes visible, and use real data.

Triage the work before moving people

Start with outcomes, not names. List the tasks that unlock the milestone and mark each as must-have, nice-to-have, or deferrable. Tie every task to a dependency so the true critical path is obvious. Many shortages disappear when non-essential work moves out of the critical window.

📚 Read more: What are milestones in project management?

Replan by role first, then confirm by skills

Avoid reactive name swapping. Rebuild the affected slice of the plan by role and required skills or certifications. Use role placeholders to test options quickly. When a pattern fits, replace placeholders with people who match availability and the must-have skills. This keeps speed and quality in balance.

Result to target: fewer context switches, faster onboarding to the hot tasks, and less rework after the milestone.

📚 Read more:4 must-have leadership skills that will lead a PM to success

Rebalance capacity, cost, and risk across the portfolio

Do not treat a shortage as a single-project issue. Look across the whole portfolio first. If one team is blocked by a scarce role, pause or push out lower-priority work that uses the same skill. Move those tasks to a later sprint so your bottleneck can focus on the milestone that matters now. If another project has Slack, borrow help for a defined window and set a clear handback date so you do not create a new problem elsewhere.

Sometimes the best move is a swap. One senior specialist can be replaced by two mid-level people if you narrow the scope and give them a tight checklist. Keep a senior on call for reviews and decisions, but let the mids carry the hours. This keeps quality steady without blowing the budget.

Before you make changes, check the impact on money and dates with your finance partner. Confirm rates, overtime rules, and vendor costs. Update your forecast so everyone sees the same new plan for effort, timing, and spend. If the numbers do not work, trim or defer lower-value tasks until they do.

Set guardrails so the team stays healthy. Cap overtime, schedule recovery days after the crunch, and watch for sudden spikes in utilization that signal burnout risk. Keep these rules visible and stick to them. With a portfolio view, clear trade-offs, and simple guardrails, you can cover the gap, protect the milestone, and avoid creating another fire somewhere else.

📚 Read more: Project portfolio risk management: tips, tools & examples

Use targeted execution tactics

Several small moves compound into stability during a crunch:

  • Decouple delivery: split tasks so specialists handle the complex core while generalists complete prep and follow-up.
  • Pair for speed: pair a senior with a mid-level to transfer context fast and reduce review loops.
  • Shift the load: move testing or documentation to time zones with the capacity to maintain a 24-hour rhythm without overtime.
  • Limit in-flight WIP: reduce concurrent tasks so limited expertise is not spread too thin.

Share one clear update everyone can trust

Send one clear update with proof so everyone sees the same truth. In a simple change log, note what changed, why it changed, the impact, and who decided. Share the new dates, people assigned, and budget impact so it‘s obvious what moved. Point everyone to a single status page and use it for every update.

How to rebalance work when resources are tight in Birdview PSA

Birdview PSA helps you adjust fast when people are in short supply. Use templates with role placeholders to replan in minutes and attach the must-have skills. Start with soft allocations to test options, then switch to confirmed bookings once you have approval. Capacity and utilization views include PTO and local holidays, so you can spot overloads early and fill gaps before they become issues. Rate cards and cost views show the budget impact of each choice, letting you protect margin before you commit. As the team logs time, dashboards refresh automatically, and built-in BI highlights utilization and schedule risk. Share the updated plan with Gantt snapshots or saved views so everyone sees the same truth.

Bottom line: when resources are tight, trim low-value work, replan by role then confirm skills, balance the load with clear cost limits.

See Birdview in action

Birdview logo
Nice! You’re almost there...

Your 14-day trial is ready! Explore Birdview's full potential by scheduling a call with our Product Specialist.

The calendar is loading... Please wait
Birdview logo
Great! Let's achieve game-changing results together!
Start your Birdview journey with a short 9-min demo
Watch demo video